HIGHRIDGE WATER AUTHORITY PROJECTS SUMMARY

REVISED as of 1/1/2014

2013

Marshall Heights Pump Station

$75,096

Replacement

 

2013

SR 56 Sec 453 Bridge Location  

$11,766

$11,766

Penn DOT Relocation

Brush Valley Twp – Brush Creek  

 

2013

SR 56 Sec N00 Bridge Relocation

500  (10″)

$66,752

$66,752

Penn DOT Relocation

Seward Borough

920  (6″)

 

2013

Forest Lane, Burrell Township

380  (6″)

$11,520

1

 

 

 

2013

SR 217 West Derry Dollar General

720  (6″)

$10,300

$37,237

1

 

 

 

2013

Roundtop/Cresswell Roads

14,000  (8″)

$111,965

$320,000

29 customers

Brush Valley Township

2,160   (6″)

 

2,340  (2″)

2010 Socialville, Burrell Twp 3240 $52,572   18
2010 Rte 22 Sec B-10 Derry Twp 6710 $118,249 $195,853 Penn DOT Relocation
2010 Long’s Rd Ext/Brush Valley Project 2810 $59,639   4
2010 Campbell St Ext/Derry Twp 300   $6,750 1 – Customer funded
2010 B.M.A. Sewage Plant Ext 2060   $55,620 1 – Customer funded
2009 Brush Valley Project 125255 $5,582,206 $645,537 425
2009 Rt 22 Relocation JugHandle G 660   $32,887 1 reconnect
2009 Rose Rd Armagh 220   $7,000 1 – Customer funded
2008 Zahornacky line extension 1530   $35,000 1 – Customer funded
2008 Germany Lutheran Cemetery Road 9500   $140,000 18
2008 Brenizer Extension 27th Street 450   $12,500 1 – Customer funded
2008 Rt 22 Clyde Relocation 1100 $18,181 $18,181 2 reconnections – PennDOT
2007 Penn View 37500 $171,976 $1,727,887 124
2007 Willow Run Bridge Derry Twp(reloc) 380 (6″) $4,493 $7,222 0
2007 Clyde Rt 259 (relocation) 10300 $220,742 $197,500 4 reconnects
2006 Ligonier Construction Derry Twp 3240   $129,600 2 – Customer funded
2006 Charles (line replacement) 655 $17,360   0
2005 Bill Dick Road (West Phila St) 1180     2
2005 Mulligan Hill 18785 $146,042 $270,000 60
2005 Horn Road Derry Twp 1500 $15,448   7 reconnects
2005 Torrance (blowoff valve relocation) 35   $4,049 Paid by Norfolk Southern
2005 Bolivar Bridge (line relocation) 825   $150,000 Paid by Penn Dot
2004 Rt 259 Replacement 500 $5,300   0
2004 Shoup Road 1750 $19,500   4
2004 Bill Dick Road 5400   $263,000 21
2003 Conemaugh River Break 315 $29,000   0
2003 Dilltown Heights & United replacement 9184 $61,000 $150,000 15
2003 Plowman Road 2340 $21,000   4
2003 Shirey Run Road 2000   $88,000 11
2002 Bracken Road 2400 $14,000   5
2002 Hillside Extension 1655 $59,000   20
2002 Seward Power Plant-replacement 4301   $364,748  
2001 County Line Road 555   $37,740 7
1999 Gas Center 62339 $1,086,213   149
1999 Bairdstown 42076 $717,173   151
1999 Dilltown 15050   $295,000 78
1999 Gas Center Tank/2 pumpstations N/A $610,440    
1998 Bolivar-relocate Tubmill crossing 1834 $124,000   6 reconnects
1997 Route 259-replacement 900 $24,213   0
1996 Strangford 18850 $100,776 $300,552 100
1996 Pizza Barn Road 8100 $150,000   40
1996 Bolivar Renovations 5980 $150,000 $180,000 118 reconnects
1995 Filtration Project/Tanks/Waterlines 14890 $7,295,815   146 RECONNECTS
1994 Climax 10448   $162,000 34